Cameras, Racks and Power · #84

Online Structured Cabling Quantity Calculator

Turns a cabling survey into a bill of materials: boxes, panels, patch cords and jacks.

  • Data is processed in your browser and not sent to a server
  • Export: CSV

Tool

name;outlets;average length (m) — optional.

If no list.

Route from rack to outlet.

Total at rack and outlet ends.

What does this tool do?

Dividing total metres by box length forgets the offcuts at the end of each box that cannot be joined, so cable runs short on site. The tool calculates how many whole runs each box yields, checks the 90 m permanent link limit and gives panel and patch cord counts.

How to use it

  1. Enter either total outlets and average length, or a zone list as name;outlets;average m.
  2. Enter ports per outlet, service slack, waste, box length and panel port count.
  3. Press Run; download the list as CSV.

Fields

Zone list
name;outlets;average length (m) — optional.
Outlets
If no list.
Average run length
Route from rack to outlet.
Ports per outlet
Service slack (m)
Total at rack and outlet ends.
Waste
Box length
Panel ports

Worked example

InputValue
Outlets48
Average run length45
Ports per outlet2
Service slack (m)3
Waste0
Box length305
Panel ports24

Expected result: 48 outlets × 2 ports = 96 runs of 48 m; 6 runs per box → 16 boxes (4,608 m), four 24-port panels, 192 patch cords, 192 jacks.

Although 4,608 / 305 = 15.1 boxes by metres, 16 boxes are needed because offcuts cannot be joined. Runs stay within the 90 m Cat6/Cat6A permanent link limit.

Second scenario

InputValue
Zone list
Kat 1;20;35
Kat 2;20;60
Depo;6;95
Ports per outlet1
Service slack (m)3
Waste5
Box length305
Panel ports24

Expected result: The warehouse zone averages 95 m and exceeds the 90 m permanent link limit; an intermediate rack or fibre is needed.

Method and assumptions

Runs = outlets × ports. Run length = average + slack. Runs per box = floor(box / (run length × (1 + waste))). Boxes = ceil(runs / runs per box). Panels = ceil(runs / panel ports). Patch cords = runs × 2 (rack + user side), jacks = runs × 2.

Using the result and troubleshooting

Add 5–10 % spare for the quote; plan an intermediate rack or fibre for long runs. Use the Rack Unit planner for the rack layout.

Limits and common mistakes

  • Averages replace route measurement; risers, ceiling/floor penetrations and containment fill must be calculated separately.

Frequently asked questions

Where does the 90 m limit come from?

Per TIA-568 and ISO/IEC 11801 the permanent link (panel to outlet) is at most 90 m and the channel including patch cords at most 100 m.

Related tools and service

Related service: PoE Switches and Camera Network Infrastructure

CCTV online tools · See all online tools